Resurfacing Station Road/New Street Padstow

Dec 16, 2016 | News

Cornwall Council will be carrying out essential resurfacing works on the above roads. The work is programmed to start on the 9th January 2017 and Cormac have a road closure for 2 weeks. CORMAC Solutions Ltd.’s Surfacing Section will be completing the work at night under a full road closure, a managed closure with marshals and convoy vehicles and temporary traffic lights.

The indicative programme (weather permitting) is as follows:
Night 1 & 2 Plane out existing surface
Night 3 & 4 reset boxes
Night 5,6 & 7 No work on site
Night 8 & 9 Relay new surface
Day 10 if the work has been completed the lines will be replaced.

  • When the road is open the vehicles will be travelling on the planed surface, the boxes and end joints will be ramped and care should be taken when driving through. Signage will be in place in site to identify the ramps.
  • Access will be maintained for these that live and work within the closure. Emergency vehicles will be given access.
  • For access and exit requirement/directions please liaise with site personnel, as this will change from activity to activity.
  • For alteration to the above programme please refer to the advance signage erected on site.

For any queries please contact 0300 1234 222 or email handee@cormacltd.co.uk stating Padstow Resurfacing.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles:

Road Closure: Trevone Road, Padstow 22-26 April 2024

The Town Council have been advised of the following road closure: Road Traffic Regulation Act 1984 S.14: Temporary Prohibition of Traffic Location:         Trevone Road, Padstow Timing:           22nd April 2024 to 26th April 2024 (09:30 to 16:00 hours daily)...

Tree works week commencing 15 April

Tree works week commencing 15 April

This week tree surgeon contractors will be on Padstow Town Council land to undertake some necessary tree works. All works are weather dependent. The contractor will close footpaths/areas, erect barriers and put up appropriate signage as necessary to make public aware....

PTC Community Grants Scheme

PTC Community Grants Scheme

The application process for 2024-25 has now CLOSED.   Please do not submit an application, it will not be considered. Eligible applications received prior to the 8 April deadline will be considered by the Finance and General Purposes Committee at a meeting to be held...