Refurbishment Works Update

Dec 11, 2019 | Car Parks, News

Lawns Car Park Improvement Works Update: Despite this awful weather the project has been progressing well.  Recent works have been focusing on the entrance which is being widened to improve access.  So far we have been able to keep the car park partially open throughout these works. 

North Quay and Cory Toilets Refurbishment Works:  This project has also been moving along.  North Quay has been totally stripped out and is now being plastered ready for the new tiles.  This week Cory was closed and the strip out works has just started.   

We appreciate your patience during these works. 

 

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles:

Railing Riverside Padstow Works Update

Railing Riverside Padstow Works Update

Despite the wet weather this week the contractor has been able to install the railings quicker then anticipated and the traffic management system has been removed. There is some smaller works still to be undertaken to complete the project (painting and some minor...